03/06/2017-CC-Minutes-Work SessionCITY OF SANGER, TEXAS
MINUTES: CITY COUNCIL WORK SESSION
March 6, 2017, 6:00 PM
502 Elm Street, Sanger, Texas
COUNCIL MEMBERS PRESENT: Mayor Thomas Muir, Councilman Bill Boutwell,
Councilman Lee Allison, Councilman David Clark, Councilman Gary Bilyeu,
Councilman Allen Chick
The Mayor and All Councilmembers were present constituting a quorum.
STAFF MEMBERS PRESENT: Mike Brice City Manager, Cheryl Price City Secretary,
Neal Welch, Director of Public Works
1. Call Meeting to Order.
Mayor Muir called the meeting to order at 6:05 p.m.
2. Update on Wastewater Treatment Plant.
City Manager Brice noted a Memo he provided to the City Council dated March 6 on the
Wastewater Treatment Plant Update. The memo read as follows, “After extensive
analysis by our consultant we are taking a multi-pronged approach to re-stabilizing the
wastewater treatment plant. He feels the biggest issue is our inability to waste solids
quickly enough. To that end we are renting and installing a temporary sludge press this
week. We hope to have it in operation by Friday. The cost of renting the sludge press is
$8500 a month and it will be necessary to keep it in operation until the permanent sludge
press is in operation as part of the plant expansion. Also, this week we will be injecting
steroids into the system to boost bacteria reproduction. Alkalinity is also out of balance
and being addressed. We are also investigating the feasibility of deodorization but do
not have enough information yet to make a decision. We continue to work with our
consultant and engineers as we strive to reduce the odor problem and get the plant re-
stabilized.” City Manager Brice noted that the cost of the temporary sludge press is
something we are going to have to endure until we get the perman ent sludge press in
place at the new plant and will request that the contractor who receives the bid on the
job get the new one in place as soon as possible. It was noted through questioning that
the sludge press would catch us up and keep us caught up because it could be done about
five times faster that we are doing it right now. The permanent sludge press will be built
inside of a building. There was a brief comment and discussion period regarding the
improvements being made to minimize the odor of the wastewater treatment plant.
3. Presentation by Alan Plummer and Associates on Stream Restoration vs Outfall
Pipeline.
Tim Noack, Alan Plummer and Associates was recognized and noted that he was here
last October when the concept of the stream restoration was introduced. He proceeded
to give an update, noting they have done some field work and some lab work and have
arrived tonight with some information that the Council will need to move forward. The
stream restoration involved some field work, some geophysical and geotechnical work.
The geophysical work was to identify how much sediment was in Paddock Lake and it is
anywhere from eight to over twenty feet deep in sediment. They also used the
geophysical work to determine the amount of limestone that was there. Unfortunately,
they found that the limestone trailed off quickly once you got past the bank. The
Geotechnical engineer went out and placed three borings and had the lab work done and
found that it was very soft clay all the way down to the bottom. It is not the best stuff on
which to build a stream channel. They also had some limited survey data that had been
taken in the lake and merged it with some LIDAR data and topography for the lake area
and looked at four different alternatives and alignments through the lake and around the
lake and tried to come up with the best alignments for it. Each of the alignments that
they did look at met the TCEQ qualifications for the discharge permit allowing for a
free-flowing stream and not allowing for any ponding to occur. They looked at the
technical feasibility of each of the options with consideration on cost and also, impacts
to the owner of the property. Three of the options were discounted and they are
presenting just one stream restoration option for consideration tonight. He referred to the
rendering below and noted Ranger Creek as it comes down from the north to the
Wastewater Treatment Plant and the outline of Paddock Lake the dam and the existing
spillway.
STREAM RESTORATION
Under this option the flow would come down Ranger Creek and they would have a
broad crested weir which would be constructed within the creek itself which would push
flows into a channel and would be constructed parallel to that channel and that channel
would be constructed in some native soil on down and would go to the edge of the lake
into an area of some shallow sediments and at that point they would take the flow into a
six-by-five box culvert and discharge it downstream of the current spillway so that there
would be free flow through that full system. He explained in detail how the water would
flow. With this option, estimated construction cost is $3,313,000, Engineering and
Permitting $468,000 (which includes current project Phase I Preliminary Engineering of
$100,000) Total project cost $3,781,000. The schedule because they are doing a lot of
the work in the lake and creek and they would have to have a 404 permit which would
take about 14 to 20 months and estimated construction 6 to 12 months (weather
dependent). There was a period of discussion and questions regarding the stream
restoration. There were a few technical questions from Councilman Allison; and,
concern was noted by Councilman Chick regarding future maintenance of the stream
option.
PIPELINE OPTIONS
The Pipeline option was presented by Chris Heckler of Alan Plummer and Associates
presented the Pipeline Discharge options. The goal was to give the City a gravity
pipeline so there is no maintenance of a pump station; and to consider the shortest
pipeline length. He presented the following options below noting the differences in
time, challenges, and cost with each plan.
He noted they have not done any Surveys, Geotechnical, just LIDAR. He noted that the
purple route is about 450 feet shorter and but may have impact being close to Mr. Riley’s
house. It may save the city about half-million dollars. Everything else, permitting, time
frame, etc. will be the same.
Councilman Allison asked if they have considered a hybrid alternative with both the
stream restoration and the pipeline? He suggested that at the point where the diversion
structure is, that they utilize a 30-inch pipeline and take it all the way down to discharge
from there. There was discussion of pros and cons of the idea. The Engineers advised
they could look at it. City Manager requested clarification of Councilman Allison’s
suggestion. Councilman Allison advised that he is suggesting they go from the plant to
the diversion structure in the stream and then taking it into a pipeline around the lake in a
30-inch or maybe a larger 36-inch pipeline. There was discussion as to how you would
keep the effluent separate from the rain. There was further pro and con discussion
between the Engineers and Councilmembers. City Manager Brice asked if they thought
that TCEQ would permit the idea. Betty Jordan with Alan Plummer and Associates was
recognized and advised that they would probably permit it but you may have lost some of
your flexibility in what you are looking at in the stream with increasing the flows in the
future without having to ratchet down on your effluent limits. You would not have quite
the flexibility that you would if you just had an open channel or a stream.
Councilmembers noted that the stream option shown was going into the box culvert.
There was additional discussion and Councilman Allison suggested bumping the pipeline
up to a 36-inch or 42-inch pipeline to give more flexibility. City Manager Brice noted
that he met with Mr. Riley a few weeks ago, and talked about the stream restoration and
Mr. Riley was very much in favor of it. He advised he gave Mr. Riley the Geotechnical
and Geophysical reports to look at. Mr. Riley has been out of town and will be back in
town in the next few days. There was concern that if you take it underground in the
pipeline that you would lose any type of free-flowing creek other than when it rains and
discussion ensued on possibly going from a 30-inch to a 36-inch pipe and what the cost
would be. It was noted that a 36-inch pipeline would be about $30-$40 per liner foot and
the pipeline may be less expensive. But that there may be the possibility of having to put
in and maintain a pump station. Betty Jordan noted that there are some intriguing
elements in this and it may save money, but may limit some flows in the future, but that
there may be some savings here. It will depend on the modeling above and how far up
you have to go. City Manager Brice asked how long it would take to have TCEQ take a
look at this idea. Betty Jordan advised that it would be just a few weeks, that they have
modeled this enough and would just need to meet with them. Councilmember Clark
advised that he would like to see us use the water again for irrigation of parks, etc. before
dumping it in the creek. Councilmember Bilyeu noted his concerns regarding the stream,
berms, etc. and future maintenance responsibilities. The engineers noted on the stream
restoration that as the geotechnical structure, vegetation, and trees grow, the
infrastructure would become more stable. The engineers advised that they could run a
new hybrid option and figure the modeling lines and how far up they have to go,
calculate the length and go bigger with the pipeline and figure out the technicalities, if it
is feasible, and come back with it; and, the other options, with pros and cons for each.
Mayor Muir noted concerns that this may become a big engineering deal, that this should
be brainstormed for maybe just an hour or so, and trade off savings for easement costs,
and find out Mr. Riley’s concerns. Discussion ensued and City Manager Brice noted first
we have to determine if it is feasible and will TCEQ Allow it. Betty Jordan advised that
before they go to TCEQ, they would meet with their permitting group and have an hou r
or so open discussion on what TCEQ would say and then would talk to Mike Brice
regarding moving forward on this. She noted the city has already paid them to do the
modeling, it is just a matter of changing out the parameters and promised they were not
going to give the city another huge bill. Mayor Muir noted that we do want to get the
best answer we can, so this exchange has been good, and we will get there.
4. Overview of Items on Regular Agenda.
There was no additional discussion of Items on the Regular Agenda.
5. Adjourn.
There being no further items Mayor Muir adjourned the Work Session at 7:06 p.m.